Task Description
Task name : |
Creating an overview guidance on floating AtoN |
||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Leading committee and working group owning the task: | ENG WG 1 | ||||||||||||||||||||||||||
Tasks associated (*leading) : | |||||||||||||||||||||||||||
Task Leader : | Gillian Burns | ||||||||||||||||||||||||||
Task Number : | ENG-2.3.2 | ||||||||||||||||||||||||||
Standards : | S1020 Marine Aids to Navigation Design and Delivery | ||||||||||||||||||||||||||
Topic area : | S1020.3 Floating Aids to Navigation | ||||||||||||||||||||||||||
Task Description : |
Creating an overview guidance on floating AtoN |
||||||||||||||||||||||||||
Objectives of the task : | Produce a guideline to support inexperienced organisations or individuals if they are required to establish floating AtoN (for whatever reason) and demonstrate the various topics to consider for the lifetime of the floating AtoN.Reference to ENG17-3.0.5 ARM Liaison Note where they note the following for the draft guideline | ||||||||||||||||||||||||||
Expected outcome : |
New Guideline on floating AtoN |
||||||||||||||||||||||||||
Compelling need : | |||||||||||||||||||||||||||
Strategic Alignment : | |||||||||||||||||||||||||||
Scope : | |||||||||||||||||||||||||||
Cybersecurity related : |
No |
||||||||||||||||||||||||||
Brief and concise description of the work : to be undertaken and programme mile-stones (where appropriate). | Intersessional work is planned to include comments from ARM18 and IALA colleagues, scheduled for Q2 or Q3 2024 (before ENG19). | ||||||||||||||||||||||||||
Expected numbers of sessions for completion : |
Meaning of symbols for sessions :
|
||||||||||||||||||||||||||
Committee notes : | Origins : | ||||||||||||||||||||||||||
Approved by Council (Council session/Date) : | 0 | ||||||||||||||||||||||||||
Notes from the council : | |||||||||||||||||||||||||||
Status (Text) : | |||||||||||||||||||||||||||
Status (Color) : |
On track
|
||||||||||||||||||||||||||
Remarks : |
|
||||||||||||||||||||||||||
History of the task : |
2024-04-11 14:51:01 The Task Group met five time during ENG18 working period, where renaming and substantial editing work on the draft Guideline was completed. The meetings were hybrid and attended by 14 participants from 8 different countries (2 online, 14 in person). 2024-11-04 19:26:46 The Task Group met twice during ENG19 working period, where comments received from ARM (Liaison Note) and China MSA (input paper) were reviewed and comments/ corrections completed in the draft document. Draft GL has been submitted for silent approval then Council approval. Liaison Note to ARM to thank them for their input. Task completed. |