VTS WG 1 Task plan
Meaning of symbols for sessions :
v | + | x | > | < |
Scheduled | Progressed | Not progressed | Finalised | On hold |
Standard | Topic Area | Task no. | Task | 54 | 55 | 56 | 57 | 58 | 59 | 60 | Status (Text) | Status (Colour) | Task leader | Remarks |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Leading : VTS | ||||||||||||||
Leading : VTS WG 1 | ||||||||||||||
S1010 Marine Aids to Navigation Planning And Service Requirements | S1010.2 Aids to Navigation planning | 1.8.1 | Develop guidance on the certification of technical equipment, information systems and technical infrastructure related to MASS in the domain of IALA | Awaiting DTEC |
Not started
|
|||||||||
1.8.2 | Review relevant sections of NAVGUIDE in cooperation with the Secretariat | Awaiting ARM |
Not started
|
|||||||||||
1.8.3 | Develop guidance on the provision of AtoN and risk management for autonomous vehicle/vessel operations (Maritime Autonomous Surface Ship, MASS) | Awaiting DTEC |
Not started
|
|||||||||||
S1010.4 Risk management | 1.8.5 | Enhancing the safety and efficiency of navigation around offshore installations | v | v | Review G1185 |
Not started
|
Trond Ski/Els Bogaert |
TC03 approved G1185 from ARM |
||||||
S1010.5 Quality management | 1.8.4 | Develop a guideline on quality management system for VTS | v | v | > | Finished |
Finished
|
Trond Ski |
TC03 approved new G1188 and revised R0132 |
|||||
S1040 Vessel Traffic Services | S1040.1 VTS Implementation | 1.1.2 | Develop guidance for establishing a compliance and enforcement framework by participating ships in a VTS area | v | v | v |
Not started
|
|||||||
1.1.3.a | Develop guidance on the implications of maritime autonomous surface ships (MASS) from a VTS perspective | v | v | v | < | < | < | < | On hold |
Delayed
|
Dorte Hansen |
The document was re-titled VTS Interaction with a Mix of Conventional, Automated and Autonomous Ships |
||
1.1.3.b | Develop guidance on the implications of maritime autonomous surface ships (MASS) from a VTS perspective | v | v | < | < | < | < | On hold |
Delayed
|
Dorte Hansen | ||||
1.1.4 | Develop guidance on delineating the VTS area | v | v | v |
On track
|
Heidi Clevett | ||||||||
1.1.5 | Develop guidance to assist competent authorities for VTS establish an appropriate policy and regulatory framework to meet their obligations | v | v | v | v | + | > | > | Ongoing |
On track
|
Els Bogaert | |||
S1040.2 VTS Operations | 1.2.1 | Develop guidance for digital route exchange within VTS operations | v | v | v |
Not started
|
||||||||
S1040.3 VTS Communications | 1.3.1 | Develop guidance on VTS digital communications | v | v | v | v | > | Ongoing |
On track
|
Jan Remi Hoeve | ||||
1.3.2 | Review and update IMO Resolution A.918(22) on SMCP | v | v | < | < | < | < | < | On hold - Awaiting IMO |
On track
|
Heidi Clevett |
Awaiting output at IMO |
||
S1070 Information Services | S1070.1 Data models and data encoding | 1.8.6 | Harmonization of VTS data elements (internal and external integration) | v | < | < | < | < |
Not started
|
|||||
No Standards | No Standards | 1.9.1 | Consider relevant VTS documents to be revised /updated | v | v | v | v | v | v | v | Ongoing |
On track
|
Trond Ski & Els Bogaert | |
1.9.2 | Continuous update of the VTS Manual | > | > | v | v | v | v | v | Ongoing |
On track
|
Neil Trainor | |||
1.9.3 | Review the VTS questionnaire and conduct a digital global survey | v | v | v | > | > | > | > | Ongoing |
On track
|
Trond Ski & Els Bogaert | |||
1.9.4 | Proceed with the "living document" on "Future VTS", including emerging technologies and Human Element | v | v | v | v | v | v | v | Ongoing |
On track
|
Neil Trainor |